Activities includes, but not limited to:
- Project Material Receiving
- Welding Consumable Material Receiving
- Pipe Stringing
- Pipe Bending
- Fabrication & Welding of Wellhead Piping
- Fabrication & welding of Tie-in Piping
- Fabrication & welding of Annuli Riser
- Welding of Pipelines
- NDT Activities
- Blasting & Painting Activities
- Fabrication & Installation of RTR Piping
- Installation of Wellhead Piping
- Installation of Tie-In Piping
- Installation of Corrosion Inhibitor Skid
- Installation of Pipe Supports
- Installation of Instrument Supports
- Installation of Valves
- Installation of Annuli Riser
- Installation of Pipeline Marker
- Bolt Torqueing
- Pigging of Pipelines
- Line Checking
- Hydro Testing of Valves
- Hydro Testing of Wellhead Piping
- Hydro Test of Flowlines
- Lay-Up (Nitrogen & Dry Lay-Up)
- Re-Manifold & Strip Out